What are liquidated damages?
Liquidated damages are a sum the parties agree in advance will be payable for a specified breach. Whether a court enforces them depends on the amount and the governing law.
What are liquidated damages?
Liquidated damages are a fixed or formula based sum that the parties agree in the contract will be payable if a specified breach occurs, most often late delivery or late completion. They spare the injured party from proving its actual loss, but a court may refuse to enforce an amount that operates as a penalty.
They are common in construction, engineering, equipment supply and large technology projects, usually as an amount per day or week of delay, with a cap.
When are liquidated damages enforceable?
Enforceability depends on the governing law. Many common law courts will enforce the sum if it was a reasonable estimate of likely loss when the contract was made, or if it protects a legitimate interest and is not out of all proportion to that interest, and will refuse a sum that operates only to punish. The exact test differs between jurisdictions. Some civil law systems allow a court to reduce an amount it considers excessive.
Other questions often matter as much: whether the clause requires notice, whether delay caused by the customer stops the clock, whether the sum is the only remedy for that delay, and how it relates to the limitation of liability. This page is general information, not legal advice.
How do liquidated damages differ from service credits?
Both are pre-agreed amounts for a defined failure. Service credits usually reduce recurring fees when a service level is missed, and some contracts describe them as a price adjustment. Liquidated damages usually compensate for a one off failure such as late completion. The legal treatment of each depends on the wording and the governing law.
What does it look like? An illustrative example
This example is illustrative and uses fictional companies. Contoso's contract with Fabrikam to build a distribution center sets liquidated damages of $5,000 for each day completion is late, capped at 10% of the $2 million contract price, which is $200,000.
Completion is 18 days late, with no delay caused by Contoso. The amount due is $90,000, inside the cap. The clause requires Contoso to give written notice within 30 days of completion, so the entitlement depends on that notice as much as on the delay.
How do you manage liquidated damages clauses?
- Record each clause with its trigger, rate, cap, notice rule and any sole remedy wording.
- Check whether an amendment or change order moved the completion date, since that moves the trigger.
- Keep evidence of the delay and its causes as the project runs.
- Send notice in the form and time the contract requires, and take legal advice before deducting disputed amounts.
How does Aavenir Atlas help?
Aavenir Atlas extracts every penalty and liquidated damages clause, with its rate, cap and notice rule, across masters, amendments and related agreements. Ask, working now, answers questions such as which supply contracts carry delay damages and what notice each requires, citing the clause. See rights and remedies and risk exposure for the wider view. Watch is in development and Recover is on the roadmap. A named person approves every action. Start your 14-day Aavenir Atlas trial.
Keep reading
Service credits Service credits are a pre-agreed reduction in fees when a supplier misses a service level set in the contract.Read more
SLA breach A supplier's failure to meet a service level in the agreement over the measurement period.Read more
Breach of contract A breach of contract happens when a party fails to perform an obligation, performs it late or badly, or makes clear it will not perform.Read more Frequently asked questions (FAQ)
Common questions
What is the difference between liquidated damages and a penalty?
Liquidated damages compensate for a breach at a pre-agreed amount. A penalty is a sum designed mainly to punish or deter, out of proportion to the interest it protects. Many common law courts refuse to enforce penalties, but the test depends on the governing law. Read about breach of contract.
Are liquidated damages the only remedy for delay?
Only if the contract says so or the law implies it. Many clauses state that liquidated damages are the sole remedy for delay, which stops a claim for larger actual losses but may leave other remedies, such as termination for long delay, in place. Read the clause with the liability terms. See contractual rights and remedies.
Do liquidated damages count toward the liability cap?
It depends on the drafting. Some contracts include them in the overall limitation of liability, some set a separate cap for them, and some do both. Read the liquidated damages clause together with the limitation clause and any amendments that changed either. See which version of a term governs.
How do I find liquidated damages clauses across my contracts?
Search for delay damages, liquidated damages, per day amounts and caps across masters, statements of work and change orders, because the rate is often in a schedule. Record each clause with its notice rule. AI extraction speeds this up across large portfolios. See contract risk exposure analysis.
Have a question we have not answered? Ask the Expert
Schedule a demo
Start your 14-day Aavenir Atlas trial.
- 1 A 30-minute Aavenir Atlas walkthrough We start from a real event, such as a price index move, an outage or an acquisition, and show the cited answers.
- 2 Then 14 days on your contracts Pick a sample of your signed agreements. We load them on our ISO/IEC 27001:2022 certified platform.
- 3 You keep the findings Every answer cites the clause it came from, so your team can check it before acting.
Prefer to talk first? Contact the team.
The form did not load. Contact the team instead, or refresh the page.